FULL RECOMMENDATION
SECTION 28(8), ORGANISATION OF WORKING TIME ACT, 1997 PARTIES : CONTRACT MANAGEMENT RESOURCES LIMITED - AND - TERENCE MARTIN DIVISION : Chairman: Mr McGee Employer Member: Mr Pierce Worker Member: Mr O'Neill |
1. Alleged non-implementation of Rights Commissioner's Decision R-031874-WT-05/TB
BACKGROUND:
2. The worker referred his case to the Labour Court on the 19th of May, 2005, for implementation. The following is the Court's determination:
DETERMINATION:
A complaint having been received under Section 28(8) of the Organisation of Working Time Act, 1997, from Terence Martin, 15, Moyclare Road, Baldoyle, Dublin 13, that his former employers, Contract Management Resources Limited, Kilbride House, 145 Pearse Street, Dublin 2, failed to implement a decision of a Rights Commissioner, No. R-031874-WT-05/TB,
And the said decision not having been carried out by the employer and no appeal having been brought against the said decision within the time limit for such appeal,
The Court hereby determines that the said employer pay to the said employee the sum of €500 in accordance with the decision of the Rights Commissioner.
Signed on behalf of the Labour Court
Raymond McGee
23rd August, 2005______________________
CON/DHDeputy Chairman
NOTE
Enquiries concerning this Determination should be addressed to Ciaran O'Neill, Court Secretary.