FULL RECOMMENDATION
SECTION 28(8), ORGANISATION OF WORKING TIME ACT, 1997 PARTIES : GALWAY PEOPLE'S RESOURCE CENTRE - AND - JOHN COMERFORD DIVISION : Chairman: Mr McGee Employer Member: Mr Carberry Worker Member: Ms Ni Mhurchu |
1. Alleged non-implementation of Rights Commissioner's Decision WT18519/04/DI
BACKGROUND:
2. A Labour Court hearing took place on the 1st December, 2004. The following is the Court's determination.
DETERMINATION:
A complaint having been received under Section 28(8) of the Organisation of Working Time Act, 1997, by John Comerford, 52 Ardilaun Road, Newcastle, Galway that his employer Galway People's Resource Centre, Canavan House, Nun's Island, Galway failed to implement a decision of a Rights Commissioner No. WT18519/04/DI dated 16th June, 2004,
And the said decision not having been carried out by the employer, and no appeal having been brought against the said decision within the time limit for such appeals,
The Court hereby determines that the said employer pay the sum of €497.20 in respect of his claim under the Act, in accordance with the decision of the Rights Commissioner.
Signed on behalf of the Labour Court
Raymond McGee
7th December, 2004______________________
JBDeputy Chairman
NOTE
Enquiries concerning this Determination should be addressed to Jackie Byrne, Court Secretary.