FULL RECOMMENDATION
SECTION 28(8), ORGANISATION OF WORKING TIME ACT, 1997 PARTIES : D.L.C. JOINERY LTD - AND - PAVEL ZIZNEVSKIJ (REPRESENTED BY RICHARD GROGAN & ASSOCIATES) DIVISION : Chairman: Mr McGee Employer Member: Mr Doherty Worker Member: Ms Ni Mhurchu |
1. Complaint of non-implementation of Rights Commissioner's Decision R-057623-Wt-07/RG.
BACKGROUND:
2. A complaint was submitted in accordance with Section 28(8) of the Organisation of Working Time Act, 1997. The following is the Court's Determination:
DETERMINATION:
A complaint having been received under Section 28(8) of the Organisation of Working Time Act, 1997 (the Act) from Pavel Ziznevskij, of 10 Bramley Grove, Castleknock, Dublin 15 (complainant) that DLC Joinery Ltd., of 21 Esmond Avenue, Dublin 3 (employer) failed to implement a decision of a Rights Commissioner, No R-057623/WT/07/RG, dated 19th July, 2008,
as the said decision has not been carried out by the employer,
and no appeal having been brought against the said decision within the time limit for such an appeal,
the Court hereby determines that in accordance with the decision of the Rights Commissioner, the said employer pay to the Complainant the sum of €3000.00 awarded in respect of breaches of the Act.
Signed on behalf of the Labour Court
Raymond McGee
3rd April 2009______________________
AHDeputy Chairman
NOTE
Enquiries concerning this Determination should be addressed to Andrew Heavey, Court Secretary.