FULL RECOMMENDATION
SECTION 28(8), ORGANISATION OF WORKING TIME ACT, 1997 PARTIES : STRESSLITE TANKS LIMITED - AND - ALGIRDAS DAUKINTIS (REPRESENTED BY RICHARD GROGAN & ASSOCIATES) DIVISION : Chairman: Mr Hayes Employer Member: Ms Cryan Worker Member: Ms Tanham |
1. Complaint of Rights Commissioners Decision has not been implemented R-080657-Wt-09/MMG.
BACKGROUND:
2. The worker referred his case to the Labour Court on the 23rd June, 2011. The following is the Court's determination:
DETERMINATION:
A complaint having been received under Section 28(8) of the Organisation of Working Time Act 1997 by Algirdas Daukintis that his former employer Stresslite Tanks Limited failed to implement a decision of a Rights Commissioner r-080657-wt-09/MMG,
And the said decision not having been carried out by the employer,
And no appeal having been brought against the said decision within the time limit for such appeal,
The Court hereby determines that the said employer pay to the said employee €1,000 in accordance with the decision of the Rights Commissioner.
Signed on behalf of the Labour Court
Brendan Hayes
30th November, 2011.______________________
CON.Deputy Chairman
NOTE
Enquiries concerning this Determination should be addressed to Ciaran O'Neill, Court Secretary.