FULL RECOMMENDATION
SECTION 28(8), ORGANISATION OF WORKING TIME ACT, 1997 PARTIES : IDM CONSTRUCTION AND SERVICES LTD - AND - VASILE BUZATU (REPRESENTED BY MARIUS MAROSAN) DIVISION : Chairman: Ms Jenkinson Employer Member: Mr Murphy Worker Member: Mr McCarthy |
1. Complaint that Rights Commissioner's Decision No: R-146858-Wt-14/Eh was not implemented
BACKGROUND:
2. A complaint was submitted to the Labour Court in accordance with Section 28(8) of the Organisation of Working Time Act, 1997. The following is the Court's Determination:
DETERMINATION:
A complaint having been received under Section 28(8) of the Organisation of Working Time Act, 1997 (the Act) by Mr. Vasile Buzatu, 11 The Gravel Walk, 50/52 Blackhall Place, Dublin 7 that, IDM Construction and Services Limited, 28 Kingston Lodge, Clonliffe Road, Dublin 3 failed to implement a decision of a Rights Commissioner, No. r-146858-wt-14/EH dated 30thMarch 2015.
And the said decision not having been carried out by the employer,
And no appeal having been brought against the said decision within the time limit for such appeals,
The Court hereby determines that the said Respondent must pay the Complainant the sum of €12,991.95. in accordance with the decision of the Rights Commissioner.
Signed on behalf of the Labour Court
Caroline Jenkinson
9th July 2015______________________
AHDeputy Chairman
NOTE
Enquiries concerning this Determination should be addressed to Andrew Heavey, Court Secretary.